Region
- Americas
Application
- Data Centers
Voltage
- 230 kV
Customer
- Arizona Public Service (APS)
Awarded
- 2023
Commissioning
- 2024
Linxon is supplying an Engineering, Procurement, and Construction (EPC) Contract to Arizona Public Service (APS) for a new 230 kV high-voltage substation that will help APS to support the rapidly growing power demand. Under the terms of the contract, Linxon is responsible for the design, engineering, construction, testing, and commissioning of the new substation, as well as the associated civil engineering and construction works. The project is expected to be completed by the end of Q4 2024.
The Goodyear Substation 230 kV project will support the expansion of a major data center in the Phoenix area, marking a significant milestone for the region’s growth and sustainability initiatives. The expansion of data centers in the Phoenix area is a crucial driver of the region’s economic growth and job creation. By enabling the expansion of data centers, the Goodyear Substation project will help provide reliable, sustainable energy solutions for the region. This project not only supports the growth and development of Phoenix, but also contributes to the wider sustainability agenda.